North Warrandyte Sewerage Project
Many customers in the North Warrandyte area can now access a piped sewerage service.
Approximately 1,000 properties that were unable to contain their wastewater on their property all year round now have the option to flush and let us take care of their wastewater. No more boggy yards and odour.
Ready to connect?
Check your property is in the North Warrandyte Community Sewerage area:
North Warrandyte sewerage area map - packages A, B & C (2MB)
North Warrandyte sewerage area map - misc construction (3MB)
Visit the relevant page for step-by-step instructions on what you need to do to connect:
Contact our Community Sewerage Program team if you're not sure which sewerage type you have at your property: 9872 2551 or [email protected]
Project updates
December 2017
Declaration of sewerage in North Warrandyte
We formally declared the sewerage service in North Warrandyte to be 'ready for use' on 21 December 2016.
Community contribution fee
As we have had a high level of interest in people connecting to the new sewer, we are pleased to advise that we have extended by another twelve months the date from which we will start collecting the Community Sewerage Contribution fee.
We will now start collecting the fee from 21 December 2018. This will allow you more time to engage plumbers to complete any works required.
If your property has not connected by 21 December 2018, a Community Sewerage Contribution fee will be added to your quarterly bill. This fee will be $26.44 per quarter for 20 years or until the property has connected.
Apply to connect to the new sewer in North Warrandyte now
Construction in progress
We are currently working on on-property pump installations (pressure customers only) in Research-Warrandyte Road and Pigeon Bank Road.
Completed works
The following works packages have been completed:
- Streetworks Package A
- Streetworks Package B
- Streetworks Package C
- Pressurised large sewerage (rising) main
- Sewage Pumping Station
- Inverted siphon main.
Sewage Pumping Station
The construction of the sewage pumping station (SPS) at the corner of Research-Warrandyte Road and Professors Lane was completed in December 2016, and the site has since been landscaped. A local landscaping contractor will be maintaining the site for a two year period. The SPS services approximately 400 properties in North Warrandyte.
Inverted siphon main
The inverted siphon main was completed in December 2016, and it connects the new sewer network with the existing Warrandyte sewerage network (south of the Yarra River). The new connecting sewer pipelines were bored beneath the Yarra River, in the vicinity of the Kangaroo Ground – Warrandyte Road Bridge.
April 2017
Declaration of sewerage in North Warrandyte
We formally declared the sewerage service in North Warrandyte to be 'ready for use' on 21 December 2016.
Apply to connect to the new sewer in North Warrandyte now
Construction in progress
- We are currently working on on-property pump installations (for pressure sewer customers only) in Kangaroo Ground-Warrandyte Road.
Completed works
The following works packages have been completed:
- Streetworks Package A
- Streetworks Package B
- Streetworks Package C
- Pressurised large sewerage (rising) main
- Sewage Pumping Station
- Inverted siphon main
Sewage Pumping Station
The construction of the sewage pumping station (SPS) at the corner of Research-Warrandyte Road and Professors Lane was completed in December 2016, and the site has since been landscaped. A local landscaping contractor will be maintaining the site for a two year period. The SPS services approximately 400 properties in North Warrandyte.
Inverted siphon main
The inverted siphon main was completed in December 2016, and it connects the new sewer network with the existing Warrandyte sewerage network (south of the Yarra River). The new connecting sewer pipelines were bored beneath the Yarra River, in the vicinity of the Kangaroo Ground – Warrandyte Road Bridge.
Contact us