Yarra Valley Water

Menu

Close menu

Clyde Street Sewer Project

To ensure the reliability of our sewerage network, we rehabilitated existing sewers in Surrey Hills.

Project history

This project commenced in 2021. The first part of these works involved construction of a new sewer main within Wharton and Clyde streets and under the pavement along Whitehorse Road, Surrey Hills. We completed these works in July 2021.

In February 2022 we commenced work on the second part of the project. This involved rehabilitating the existing sewer with a technique called slip lining within private properties. 

Unforeseen ground conditions meant a pause to the project at that time and we’ve since been working on a long-term solution that will involve completing the works in 2 separate stages.

A combination of wet weather, site challenges and resources have prevented us from completing the entire project in 2022. By December, we completed most of the first part of our works.

August 2023

We've recently circulated a project update to residents in the works area.

View the latest update

May 2023

We’ve recently circulated a project update to residents in the works area.

View the May 2023 update

December 2022

We’ve recently circulated a project update to residents in the works area.

 View our December 2022 bulletin 

 

July 2021

Stage 1 construction complete

Thank you for your patience while we completed Stage 1 of the Clyde Street Sewer Project. 

After building the pipeline and maintenance holes, we completed a series of tests before commissioning the new sewer. It’s now operational and linked to our broader sewerage network.

Stage 2 work will need us to access to private property, and we’ve contacted residents who will be impacted by our work.

What we did

Using laser-guided micro-tunnelling equipment, we installed pipes in Clyde Street, Whitehorse Road and Wharton Street.

We built deep launch and retrieval shafts - and constructed new maintenance holes that will be used by our operations and maintenance teams.
Given the depth and size of the shafts, Clyde Street and Wharton Street were closed to traffic.

Construction started in mid-March and was completed by mid-July. Commissioning was completed in late July 2021.

There was no interruption to your water and sewerage services during our work.

Download this update (PDF, 499KB)

Map 

The map shows where we were working in Surrey Hills.

View map of work location (PDF)

June 2021

In March 2021, our project partner MFJ Construction started work on the Clyde Street Sewer Project. The new sewerage pipes are now in place and we’re more than halfway to completing the project. We expect to complete Stage 1 works by early July 2021.

Clyde Street Community Update June (PDF 685KB)

March 2021

STAGE 1 CONSTRUCTION WORK HAS STARTED
In March, MFJ Constructions started on the Clyde Street Sewer Project. Our new sewer will be constructed in sections – starting in Clyde Street, then working along Whitehorse Road and into Wharton Street, Surrey Hills. This project is expected to take six months to complete, subject to weather and ground conditions.

View the bulletin sent to residents March 2021 (PDF 375KB)

February 2021

We're replacing a section of the sewerage network in Surrey
Hills. While the existing sewerage system continues to function,
our Clyde Street Sewer Project will provide a long-term solution
for ensuring reliability in your area.

View the February 2021 bulletin (PDF 398KB)

Contact us

For more information, contact Katherine Collette, Project Manager, on 9872 1832 or email [email protected].